Bringing it all together one element at a time

Bringing it all together one element at a time

Progress Update: Eighteen

It's been a hectic week onsite (once again) with some of our trades working 13 hour days, weekend work and battling the heat and rain of the weather. However our builder Luke is managing to delicately juggle each piece of the build-puzzle one element at a time, including the important final stages of rough-ins taking place downstairs. 

As per our sneak peek on Facebook earlier this week, our upstairs custom kitchen cabinetry and cornice has now been installed, with the final fit-off taking place next week (which includes hanging doors, locks, skirting and architrave).  

 

Author: WVS Admin
0 Comments
Article rating: No rating
Plaster, Paint and Progress

Plaster, Paint and Progress

Progress Update: Seventeen

Happy Friday after another busy week onsite! We will be keeping today's post short n' sweet as the picture gallery really tells today's story.

As you can see our plasterers and setters have officially entered the building. The second storey exterior has a complete two coat paint job and internal walls will commence next week with cabinetry.

You'll also notice the air conditioning cassettes hanging from the downstairs ceiling. This was a special requirement of the build.

Author: WVS Admin
0 Comments
Article rating: No rating
The biggest transformation has hit

The biggest transformation has hit

Progress Update: Sixteen

As we draw to the end of week 18 in our build process (which was infact also a short week due to Australia Day) we are amazed at the considerable progress of all our trades. We arrived this morning to gangs of men, utes aplenty and the tools of 17 contractors buzzing around site - each with a task and mission of their own to form part of our overall build.

The (heavy) exterior Pronto Panel cladding is almost fully complete giving the entire building its protective shell.

Author: WVS Admin
0 Comments
Article rating: No rating
Taking shape in Pronto Panel

Taking shape in Pronto Panel

Progress Update: Fifteen

Last Friday we all enjoyed seeing the first exterior Pronto Panel cladding fixed into position which was soon followed this week by the very last fixed to the second floor. It's all becoming very exciting now finally seeing the building take its shape and form!

Downstairs the interior and ceiling has also been sheeted in what our labourer Braiden calls itchy insulation, giving you a real sense of the size and space. Upstairs has also seen the walls insulated with plasterers booked to commence onsite today. 

Author: WVS Admin
0 Comments
Article rating: No rating
Windows, Paper Wrap & Pronto Panelling

Windows, Paper Wrap & Pronto Panelling

Progress Update: Fourteen

It's now two weeks into the New Year and things at the jobsite are looking fantastic! After a lull over the Chrissie break (which was to be expected) the premises is bursting at the seems with products ready for install (including Lisa's garage). 

It's been a big week of "rough ins" which basically means the main trades (plumbing and electrical) setting up their equipment and laying pipes and cableing in preperation for connection. The carpentry team have also been busy installing the last of the windows (some even double glazed in the reception area to keep our customers cooler), wrapping the exterior in blue paper, insulating the internal walls.

Author: WVS Admin
0 Comments
Article rating: No rating